๐๐๐๐จ๐ซ๐ ๐ญ๐ก๐ ๐๐๐ข๐ฌ๐ ๐๐ญ๐๐ซ๐ญ๐ฌ
Upstream raises work only when the beach stays dry and the water stays controlled.
Most problems in upstream construction donโt start at the crest.
They start long before the first lift is placed.
As the construction season approaches, mining operations in cold climates are planning for the annual tailings embankment raise.
With a short window and very little room for error, this is the moment where discipline matters more than speed.
Before equipment moves, a few checks decide whether the raise will be routine or stressful.
๐ Pre-raise check
Confirm the approved raise design, instrumentation status, trigger levels, and baseline conditions. Proceed only when conditions are approved by the EoR.
Starter berm construction
Build the starter berm using engineered local soil or rock, placed in controlled lifts and compacted to specification.
Drainage works
Construct and commission the designed drainage system to manage seepage and surface water before deposition begins.
If these steps feel slow, theyโre doing their job.
Theyโre what make everything that follows possible.
Upstream construction looks simple on drawings. In the field, itโs unforgiving.
Once deposition begins, control shifts from design to execution
Tailings deposition (beach development)
Deposit tailings from spigots along the crest or starter berm to build and maintain a competent beach and keep the pond away from the embankment.
Borrow preparation
Excavate tailings only from the beach zone, away from the pond and saturated areas, once trafficable conditions are confirmed.
Raise construction
Place approved borrow material on the crest in thin lifts and compact to form the new berm or lift.
Monitoring and controls
Continuously monitor instrumentation, verify performance against trigger thresholds, and suspend activities if limits are exceeded.
Most issues in cold-climate tailings dams donโt come from bad design.
They come from rushing steps, losing water control, or assuming the beach is โgood enough.โ
For junior engineers, understanding this framework early makes site decisions easier to read and mistakes much harder to make.
Upstream raises donโt fail because engineers donโt know the theory.
They fail when discipline slips in the field.Control the water, respect the beach, and the embankment will take care of itself.ย
#TailingsEngineering #GeotechnicalEngineering #MiningEngineering #RiskManagementย