Shovel-truck systems represent the most prevalent method for transporting raw materials in open-pit mining, yet they impose substantial financial demands. Haulage operations alone account for 50% to 60% of total mining operating costs and can reach 60% to 75% of raw material expenses in deep open pits. Consequently, fleet sizing constitutes a critical balancing act between equipment productivity and capital expenditure. Additional trucks increase excavator utilization, but individual truck productivity declines as road congestion and queuing intensify. Mine planners must therefore identify an optimal fleet size that satisfies production targets while minimizing both idle machinery and unnecessary capital waste.
Fleet sizing begins with the required shift tonnage or volume and the scheduled shift duration. Planners must determine each truck’s actual load per trip by adjusting its rated payload with an empirical fill factor. Mixed fleets require separate modeling for each vehicle class, because assuming a uniform single-class fleet can underestimate maximum production capacity by up to 14% when two truck classes operate together. Furthermore, scheduled hours must be converted into true working hours without double-counting delays. Physical availability removes mechanical downtime, use of availability deducts standby periods such as shift changes and breaks, and operating efficiency accounts for running delays like refuelling.
Total haulage cycle time encompasses spotting, queuing at loaders and dumps, loading, loaded travel, dumping, and empty return. Rather than relying on idealized single-cycle figures, planners should use multi-shift averages recorded by fleet management systems. Travel durations shift continuously as pit depth increases and faces advance, driven primarily by haul road geometry and surface quality. Uphill speeds decline with steeper grades and heavier payloads, with deceleration accelerating sharply above a 4% grade. Soft or poorly maintained surfaces can elevate rolling resistance from 1.2% to 20%. Inadequate road width, sharp curves, busy intersections, vehicle condition, and operator fatigue further extend cycle times.
Effective circuit design requires physical compatibility between loaders and trucks, including appropriate bench height, dump clearance, and a target of three to six bucket passes. A match factor below 1.0 leaves loaders waiting, whereas values above 1.0 generate truck queues without adding tonnage. Because trucks bunch on ramps, static averages fail to capture stochastic arrival variability and shift-change effects. Discrete-event simulation addresses this limitation; one case study showed that 13 trucks could meet a 15,000 BCM daily target instead of 17, saving $180 per hour. Long-term sizing also weighs capital expenditure against maintenance and production-loss costs, often justifying strategic spare capacity.
Optimum haulage fleet size cannot be established through a static, one-time arithmetic formula. Instead, mine planners must integrate shift production targets and equipment availability with haul road physics, loader-truck compatibility, stochastic queuing behavior, and life cycle economics. Conventional cycle-time and match-factor equations provide a useful baseline estimate for initial planning. Before committing capital or parking existing vehicles, however, operations should validate fleet configurations against historical dispatch data using queuing models or discrete-event simulation. As pit geometry evolves and haul distances lengthen, continuous re-evaluation of truck counts and dispatching strategies remains essential for sustained operational efficiency.